Economic land in Algeria: the full pathway, from pre-registration to the sale deed

📌 In short: Obtaining economic land is not a single formality but an eleven-stage pathway, each stage with its own deadline. Executive Decree no. 26-154 of 14 April 2026, published in Official Gazette no. 31 of 28 April 2026, rewrote several of them and tightened most: 30 days of display, 15 days of processing, 48 hours to reply after the board's decision, 8 days to sign the specifications, 8 days for the concession deed, 3 months for conversion to sale. Here is the full chronology, and what keeps running after signature.

Keywords in this article

economic land procedure concession convertible to sale investor digital platform specifications conversion to sale appeal to the High Commission 30-day display concession deed 8 days annual rental fee building permit 2 months start of works 6 months AAPI one-stop shop

1. Stages 1 to 3: from displaying the plot to a registered application

Everything starts on the investor digital platform, managed by the Agency. Available property is displayed there, accompanied by a technical sheet specifying the expected activity.

1

Display of the plot — 30 days

Article 4 sets the display period at thirty days. That is the window during which applications are admissible.

2

Online pre-registration

The applicant completes, via the platform, the headings of the project: the intended activity, the location and area of the targeted property, and the financing plan — projected project cost, amount of personal contributions and amount of loans.

3

Confirmation and automatic receipt

"The applicant confirms the choice and formalises the registration of the application against a registration receipt generated automatically by the investor digital platform."

At this stage the required documents are attached, including the techno-economic study complying with the Annex V template and the evidence of financial capacity, which we detail in our article on the techno-economic study template.

Any natural or legal person, domestic or foreign, resident or non-resident within the meaning of Law no. 22-18 on investment, holding an investment project, may apply.

2. Stages 4 to 6: scoring, pre-selection and decision

Processing is digital and follows a strict sequence.

StageContentDeadline
4. ProcessingScoring via the Annex I evaluation grid, cross-referenced with the targeted plot; ranking in descending order of score15 days from expiry of the display period
5. Pre-selectionList of projects ranked in the top three score levels, whose information has been found consistent with the required documents
6. DecisionList submitted anonymously to the board, which selects the beneficiary projectNext board session; Agency reply within 48 hours of the decision

The board rules "taking into account, in particular, the score obtained, the coefficient of each criterion, the parameters, the importance of the project and its impact on the national economy". The scoring is covered in detail in our article on the evaluation grid out of 1,500 points.

The Agency then issues a provisional decision of award, using the model in Annex II to the decree.

Is your file ready for the 30-day window?

The display lasts thirty days and processing fifteen. We prepare the techno-economic study, the financial capacity evidence and the consistency of declared data in advance.

Prepare my application →

3. Stage 7: the provisional decision becomes final

A point often misunderstood: the award decision is not immediately final.

📜 "The provisional decision becomes final only after expiry of the appeal periods provided for by Presidential Decree no. 22-296 of 4 September 2022."

An unsuccessful applicant may lodge a complaint and then, where the outcome notified via the platform is unfavourable, an appeal to the National High Commission for Investment Appeals.

  • If the appeal is inadmissible or rejected, the Agency notifies the final decision authorising the concession in favour of the selected investor, using the model in Annex III.
  • If the appeal is upheld, the successful appellant is informed of the final decision; the Agency cancels the provisional decision and notifies the initial beneficiary.

The decree also covers subsequent cancellation: the board then selects, at its next session, a new beneficiary from the pre-selected list, or decides to return the property to the economic land portfolio.

Collecting the final decision: the beneficiary is invited to contact the territorially competent one-stop shop within a period not exceeding fifteen days from expiry of the appeal periods or from notification of the High Commission's decision.

4. Stages 8 and 9: specifications and concession deed

This is where the calendar tightens and commitments become binding.

StageDeadlineBasis
One-stop shop's invitation to sign the specifications48 hours from collection of the final decisionArt. 9 bis
Investor's signature of the specifications8 days from notification via the platformArt. 9 bis
Concession deed drawn up by the state property representative8 days from receipt of the fileArt. 11
Taking possession of the propertyReport drawn up by the one-stop shop as soon as the deed is issuedSpecifications, Art. 20

Signing the specifications "commits the investor to carrying out the planned investment project in full compliance with its clauses and conditions". And Article 9 bis recalls that "the beneficiary investor is bound to comply with the declarations made when formulating the application".

⚠️ The penalty for silence. Failure to comply, "after one (1) formal notice that has remained without effect for ten (10) days, results in cancellation of the economic land award decision". One notice, ten days: the margin is narrow.

Article 13 sets out what the concession opens in return: it "entitles its holder to obtain the building permit and all authorisations, approvals and administrative documents enabling effective implementation of the investment project, from the investment one-stop shops".

5. Stage 10: the construction phase and its obligations

The standard specifications annexed to the decree govern execution through a series of deadlines and commitments.

ObligationDeadline
Filing the building permit application at the one-stop shop2 months from issuance of the concession deed
Start of construction works6 months from obtaining the building permit
Completion and entry into operationPeriod stated in the specifications, from obtaining the building permit
Payment of the annual rental fee15 days from receipt of the payment order
Project progress reporthalf-yearly, submitted to the Agency through its one-stop shop
Agency's reply to a change-of-activity request1 month from referral

The annual rental fee is "payable from the entry of the project into operation". In the event of late payment, the state property collector gives formal notice to pay "within eight days" the amount increased by a 5% penalty; failing which, the collector refers the matter to the Agency's one-stop shop to terminate the concession.

The investor must also notify the Agency, through the one-stop shop, of "any changes to any element concerning the investment project".

6. Stage 11: converting the concession into a sale

This is the culmination of the scheme: moving from a right of use to ownership.

A

Processing the request — 3 months

Article 15 as amended provides for a period "not exceeding three (3) months from the date of receipt of the request".

B

Drawing up the sale deed — 15 days

"The state property representative at the Agency's one-stop shop draws up the sale deed within a period not exceeding fifteen (15) days from the date the file is transmitted."

C

Costs borne by the investor

The specifications place on the investor the registration duties, the land publicity tax on the sale deed, and all other duties and taxes in force when the deed is drawn up.

Termination, at the other end of the pathway

Article 17 governs exit from the scheme. Termination may be initiated by the Agency, through its one-stop shop, in particular where the concession holder fails to meet its commitments. It requires formal notices that have remained without effect, the first issued and sent by the Agency, the next served by a bailiff for the same period. On the basis of the notified termination decision, the state property representative at the one-stop shop draws up the termination deed.

🔎 Field observation (our engagements, not a regulatory text). The pathway is short on paper and long in practice, for a simple reason: most deadlines run from an act the investor must initiate — collecting a decision, signing specifications, filing a permit application. It is the waiting days between those acts, not the administrative deadlines, that stretch the real calendar.

This article reproduces the procedure as organised by Executive Decree no. 26-154 and the annexed standard specifications; it constitutes neither legal advice nor a guarantee of obtaining economic land. The text may be amended: verify it with AAPI or in the Official Gazette before filing.

FAQ — Frequently asked questions

How long is a plot displayed on the digital platform? +
Article 4 of Executive Decree no. 23-487, as amended by Decree no. 26-154, sets the display period at thirty days. Registered applications are then processed within a period not exceeding fifteen days from expiry of the display period, and submitted to the board at its next session.
Can a foreign investor apply for economic land? +
Yes. The text provides that any natural or legal person, domestic or foreign, resident or non-resident within the meaning of Law no. 22-18 on investment, holding an investment project, may apply for a mutual-agreement concession convertible to sale of a property forming part of the State's private domain.
When does the award decision become final? +
The provisional decision becomes final only after expiry of the appeal periods provided for by Presidential Decree no. 22-296 of 4 September 2022. The beneficiary is then invited to contact the territorially competent one-stop shop within a period not exceeding fifteen days to collect it.
What is the deadline for filing the building permit application? +
The standard specifications provide that the concession holder must file the building permit application at the territorially competent one-stop shop within a period not exceeding two months from issuance of the concession deed. Works must start within a period not exceeding six months from obtaining the permit.
How long does converting a concession into a sale take? +
The request is processed within a period not exceeding three months from the date of receipt. The state property representative at the one-stop shop then draws up the sale deed within a period not exceeding fifteen days from transmission of the file.
What happens if the fee is paid late? +
The concession holder has fifteen days from receipt of the payment order to settle the annual rental fee. Beyond that, the state property collector gives formal notice to pay within eight days the amount increased by a 5% penalty. Failing which, the collector refers the matter to the Agency's one-stop shop to terminate the concession.

🔎 Sources and references

📚 Related articles on ProfitPilot

BENSAID Farouk ProfitPilot

BENSAID Farouk

Financial & Economic Research Consultant — ProfitPilot NextGen Consulting

Certified sole trader and expert in financial studies, risk analysis and market research for SMEs, startups and investors in Algeria. View full profile →