The economic land scoring grid: how your project is rated out of 1,500 points

📌 In short: Allocating economic land is not a matter of judgement: it rests on a quantified scoring grid, published as Annex I to Executive Decree no. 26-154 of 14 April 2026. Eight criteria, coefficients ranging from 1 to 7, and a maximum score of 1,500 points. Applications are processed digitally, ranked in descending order of score, and only projects falling within the top three score levels are pre-selected. Understanding the real weight of each criterion means knowing where an application is actually decided.

Keywords in this article

economic land scoring grid scored out of 1,500 annex I decree 26-154 nature of activity coefficient 7 own funds contribution local content rate job sustainability fixed-term top three score levels investor digital platform priority 1, 2, 3 adjoining property AAPI investment

1. Digital scoring, a ranking, and three levels retained

Executive Decree no. 26-154 of 14 April 2026, published in Official Gazette no. 31 of 28 April 2026, rewrites Article 7 of Decree no. 23-487. Processing of an economic land application "is carried out digitally, by means of the project evaluation grid, the model for which appears in Annex (I) attached to this decree, cross-referenced against the property targeted by the applicant".

Three procedural points are worth noting before even looking at the criteria.

1

Ranking is automatic

It is carried out "digitally, in descending order of the score obtained". No human judgement intervenes at this stage.

2

Only three score levels are pre-selected

The Agency draws up a list of projects ranked in the top three score levels, whose declared information has been examined and found consistent with the required documents. A single level may contain several projects with the same score.

3

The board decides anonymously

The list is submitted anonymously by the director general, together with the examination and evaluation sheets. The board decides "taking into account, in particular, the score obtained, the coefficient of each criterion, the parameters, the importance of the project and its impact on the national economy".

📌 What this implies. The score does not decide alone, but it decides access to the decision: outside the top three levels, the file never reaches the board. The first objective is therefore not to be the best, but to enter the zone where you are examined at all.

2. The full grid: eight criteria, coefficients and scores

Here is the Annex I grid, reproduced in full. The "score" column is the parameter value multiplied by the criterion's coefficient.

CriterionCoef.ParameterValueScore
Nature of the activity7Priority 160420
Priority 240280
Priority 320140
Investment amount6≥ 100 billion DA60360
50 ≤ amount < 100 billion DA55330
10 ≤ amount < 50 billion DA50300
7 ≤ amount < 10 billion DA40240
5 ≤ amount < 7 billion DA35210
2 ≤ amount < 5 billion DA30180
1 ≤ amount < 2 billion DA20120
0.5 ≤ amount < 1 billion DA1590
0.1 ≤ amount < 0.5 billion DA1060
< 0.1 billion DA530
Own funds contribution4Contribution ≥ 70%50200
50% ≤ contribution < 70%40160
30% ≤ contribution < 50%30120
Contribution < 30%2080
Employment5≥ 500 jobs60300
250 ≤ jobs < 50050250
100 ≤ jobs < 25040200
50 ≤ jobs < 10030150
10 ≤ jobs < 5020100
< 10 jobs1050
Job sustainability1Fixed-term contracts < 20%6060
20% ≤ fixed-term share < 30%4040
Fixed-term share ≥ 30%1010
Investment extension1Adjoining property7070
Other property3535
Contribution to export diversification1Share > 50%3030
25% ≤ share ≤ 50%2020
Share < 25%1010
Share = 000
Local content (integration rate)2Rate > 50%3060
25% ≤ rate ≤ 50%2040
Rate < 25%1020
Rate = 000
Maximum score1,500

3. The real weight of each criterion: four lines make 85% of the score

Read line by line, the grid suggests the eight criteria carry similar weight. Set against the maximum of 1,500 points, it tells a different story.

CriterionMaximum scoreShare of total
Nature of the activity42028%
Investment amount36024%
Employment30020%
Own funds contribution20013.3%
Investment extension704.7%
Job sustainability604%
Local content604%
Export diversification302%

The first four criteria represent 1,280 points out of 1,500, or 85% of the score. The last four combined cap out at 220 points — less than the employment criterion alone.

The decisive criterion: nature of the activity

With a coefficient of 7 and a spread from 420 to 140 points depending on priority, this is the heaviest and most discriminating criterion. Yet it does not depend on the project's financial structure: priorities "are determined by the Agency, in consultation with the sectors concerned and the walis, on the basis of a study of investment intentions expressed by project sponsors, and settled after deliberation by the board".

The text adds a decisive detail: the property on offer is accompanied, when displayed on the digital platform, "by a technical sheet specifying the criterion relating to the activity specific to the property concerned".

⚠️ Practical consequence. The priority 1, 2 or 3 classification is read on the technical sheet of the plot you are targeting, before applying. Applying for a property whose technical sheet does not match your activity means accepting a 280-point gap out of 1,500 from the outset — rarely recoverable through the other criteria.

What score would your project achieve?

We simulate your score across the eight criteria of the grid, identify the recoverable points, and align the techno-economic study with the figures you declare.

Simulate my project's score →

4. The financial criteria: amount and contribution are read together

The grid carries an explicit reading note for criteria 2 and 3: "The correlation between the two criteria allows an assessment of the investor's capacity to raise the financing needed to carry out the project."

In other words, these two criteria are not independent. Announcing a large investment to capture the 360 points for amount while declaring a contribution below 30% produces a readable combination: 360 + 80 = 440 points, but above all an apparent inconsistency between stated ambition and demonstrated means.

Three combinations, at the same investment amount

A worked reading, for a 3 billion DA project — 180 points for the amount:

Declared contribution"Contribution" scoreTotal of the two criteria
≥ 70%200380
50% to 70%160340
30% to 50%120300
< 30%80260

The gap between the best and worst contribution scenario is 120 points — equivalent to two investment amount brackets. A more modest but strongly self-financed project can therefore outrank a more ambitious but thinly capitalised one.

Remember that the declared contribution must be evidenced: the decree requires proof of financial capacity, including a bank statement or financial statements. We cover this in our article on the techno-economic study template, and its link with bank financing in the one on the own contribution banks actually require.

5. The secondary criteria: few points, but easy to win

The last four criteria total only 220 points. They are nonetheless the most neglected — even though they turn on project design choices rather than additional resources.

  • Investment extension (70 points). An adjoining property is worth 70 points, against 35 for any other. The reading note specifies that this criterion "takes into account experience in the field concerned". An investor already established therefore has an interest in targeting an extension rather than a new site.
  • Job sustainability (60 points). The parameter is the share of fixed-term contracts: under 20% is worth 60 points, 30% or more only 10. A 50-point gap obtained through a single contracting-structure choice.
  • Local content (60 points). The integration rate is calculated as "the value of locally produced inputs relative to total inputs of the manufactured product". Exceeding 50% doubles the score compared with a rate below 25%.
  • Export diversification (30 points). Calculated as "the share of exports in projected output". It is the lightest criterion, but costs nothing to document where the project has an export purpose.

🔎 Field observation (our engagements, not a regulatory text). In the files we are asked to rework, these four criteria are rarely quantified: the integration rate and export share are often left blank or filled in by guesswork. Yet they are the only points on the grid obtainable without increasing either investment or headcount — provided they are calculated and documented in the study.

6. Preparing your application: the order of decisions

Observations from our advisory practice, not regulatory provisions.

  1. Read the property's technical sheet first. It sets the expected activity, and therefore the 420-point criterion. That choice precedes all others.
  2. Simulate the score before filing. All eight criteria are public and quantified: a simulation table takes an hour to build and avoids a wasted application.
  3. Arbitrate between amount and contribution, don't just maximise the amount. The two are read together; unfunded ambition shows.
  4. Quantify the four secondary criteria in the study. Integration rate, export share, fixed-term share, adjacency: these are figures to calculate, not intentions to declare.
  5. Check consistency between the grid and the techno-economic study. Headcount, amount and contribution declared in the application must match those in the study. A divergence between the two documents is the leading ground for non-conformity.

This article reproduces the evaluation grid published as Annex I to Executive Decree no. 26-154; it constitutes neither legal advice nor a guarantee of obtaining economic land. The text may be amended: verify it with AAPI or in the Official Gazette before filing.

FAQ — Frequently asked questions

What is the maximum score on the economic land evaluation grid? +
The maximum score is 1,500 points, spread across eight criteria with coefficients from 1 to 7: nature of the activity (420 points), investment amount (360), employment (300), own funds contribution (200), investment extension (70), job sustainability (60), local content (60) and contribution to export diversification (30).
Which criterion carries the most weight? +
The nature of the activity, with a coefficient of 7 and a maximum of 420 points, or 28% of the total. The priority 1, 2 or 3 classification is determined by the Agency in consultation with the sectors concerned and the walis, and appears on the technical sheet accompanying the display of the property on the investor digital platform.
How are projects selected after scoring? +
Ranking is carried out digitally in descending order of score. The Agency draws up a list of pre-selected projects ranked in the top three score levels, whose declared information has been found consistent with the required documents. That list is submitted anonymously to the board, which decides taking into account the score, the coefficient of each criterion, the parameters, the importance of the project and its impact on the national economy.
How is the integration rate calculated? +
The grid's reading note specifies that it is calculated as the value of locally produced inputs relative to total inputs of the manufactured product. A rate above 50% is worth 60 points, between 25% and 50% is worth 40, below 25% is worth 20, and a nil rate scores nothing.
Does a high contribution offset a modest investment? +
Partly. The gap between a contribution of 70% or more and one below 30% is 120 points, roughly equivalent to two brackets of the investment amount criterion. The grid itself notes that the correlation between these two criteria allows an assessment of the investor's capacity to raise the necessary financing.
Does the share of fixed-term contracts really affect the score? +
Yes, by 50 points. A share of fixed-term contracts below 20% is worth 60 points, between 20% and 30% is worth 40, and 30% or more only 10. This criterion reflects the objective of creating sustainable jobs set out in Law no. 22-18 on investment.

🔎 Sources and references

📚 Related articles on ProfitPilot

BENSAID Farouk ProfitPilot

BENSAID Farouk

Financial & Economic Research Consultant — ProfitPilot NextGen Consulting

Certified sole trader and expert in financial studies, risk analysis and market research for SMEs, startups and investors in Algeria. View full profile →