NPV, IRR and payback period: is your project profitable before you borrow?

📌 In short: Part VI of the template imposed by Annex V to Executive Decree no. 26-154 requires four indicators: IRR, NPV, break-even point and margin rate. These are not boxes to fill: they are four answers to a single question — does the project create more value than it costs, and from when? This article explains what each indicator measures, how it is calculated, and works them through a complete numerical example, from the initial investment to the decision.

Keywords in this article

NPV IRR calculation net present value internal rate of return discounted payback period discount rate projected cash flows break-even point worked example annex V part VI cost of financing profitability study algeria investment decision

1. Four indicators, one question

A project can be useful, well designed and led by a strong team, and still be a poor financial decision. The four profitability indicators exist to settle that point, and nothing else.

IndicatorThe question it answers
NPV — net present valueDoes the project create value once future money is brought back to today's terms?
IRR — internal rate of returnWhat financing rate can the project bear before it stops being profitable?
Payback periodAfter how long is the initial outlay recovered?
Break-even pointFrom what activity level does the result turn positive?

These four indicators are expressly required in economic land applications: Part VI of the template in Annex V to Executive Decree no. 26-154 of 14 April 2026 calls for a projected income statement, cash flow statement and balance sheet over three to five years, together with a "profitability analysis" covering IRR, NPV, break-even point and margin rate. We set out that template in our article on the techno-economic study required by AAPI.

📌 The common starting point: cash flows. None of these indicators is calculated on accounting profit. They are calculated on net cash flows — what actually comes in, less what goes out. A project can report an accounting profit while destroying cash; that is precisely what these calculations reveal.

2. NPV: bringing future money back to today

A dinar received in five years is not worth a dinar received today: you have to wait, and waiting has a cost. NPV corrects for that by discounting each future flow, then subtracting the initial investment.

NPV = Σ [ cash flow of year n ÷ (1 + r)n ] − initial investment

where r is the discount rate and n the year number.

How to read the result

  • Positive NPV: the project returns more than the required rate. It creates value.
  • Zero NPV: the project returns exactly the required rate, no more, no less.
  • Negative NPV: the project does not cover the cost of the capital raised, even if it shows an accounting profit.

Choosing the discount rate

This is the most structuring decision, and the least explained in applications. The discount rate represents the minimum return required given the cost of the resources raised and the project's risk. It is generally built from the average cost of financing — bank share and own contribution combined — plus a premium for the specific risk of the activity.

None of the texts we examined sets a regulatory discount rate for these studies. The rate is therefore a matter of the author's judgement — which makes it essential to state and justify it in the study, failing which the NPV cannot be verified.

3. IRR: the rate your project can bear

The IRR is the discount rate that makes NPV exactly zero. It is therefore the project's own return, independent of how it is financed.

Reading it is straightforward:

SituationInterpretation
IRR > cost of financingThe project supports its financing and generates a margin. Positive NPV.
IRR = cost of financingExact break-even. No safety margin.
IRR < cost of financingThe project does not cover its resources. Negative NPV.

The gap between the IRR and the actual cost of financing is the project's safety margin: it is what the structure can absorb in rate increases, cost overruns or start-up delays before it tips over.

⚠️ Two limitations to know. The IRR implicitly assumes that the cash generated is reinvested at that same rate, which is rarely the case. And where flows change sign several times — a project requiring heavy reinvestment midway — several mathematically valid IRRs can exist. In both cases, it is the NPV that settles the matter.

4. The payback period: simple, then discounted

The payback period answers the most intuitive question: after how many years is the initial outlay recovered? There are two versions, and the gap between them is instructive.

1

Simple payback

Cash flows are accumulated year by year until they reach the amount invested. Easy to calculate and easy to grasp — but it ignores the cost of time entirely.

2

Discounted payback

Flows are accumulated after discounting. Always longer than simple payback, it is the only version consistent with NPV and IRR.

This indicator measures not profitability but risk exposure: the longer the period, the more the project depends on distant, and therefore fragile, assumptions. A banker often reads it before the NPV, because it maps directly onto the tenor of the loan they would grant.

The break-even point, on the same logic

The break-even point completes the picture by reasoning in volume rather than years: it is the activity level at which revenue covers all costs. It maps directly onto the production capacity declared in the technical part of the study — and that cross-check is what gets verified.

5. A complete worked example

The figures below are illustrative: they serve only to show how the calculations follow from one another.

Assumptions. Initial investment of 100,000,000 DA in year 0. Projected net cash flows over five years. Discount rate applied: 12%.

YearNet flow (M DA)Factor at 12%Discounted flow (M DA)Cumulative
118.000.892916.0716.07
226.000.797220.7336.80
332.000.711822.7859.58
434.000.635521.6181.18
536.000.567420.43101.61

The four results

IndicatorCalculationResult
NPV at 12%101.61 − 100.00+1.61 M DA
IRRNPV = +1.61 at 12%; NPV = −1.14 at 13%≈ 12.6%
Simple paybackUndiscounted cumulative: 18 · 44 · 76 · 110 → between years 3 and 4≈ 3.7 years
Discounted paybackDiscounted cumulative: 81.18 at year 4, 101.61 at year 5≈ 4.9 years

What these four figures say together

The project is profitable, but only just. NPV is positive, so it creates value at the required rate. But an IRR of 12.6% leaves only 0.6 points of margin above the discount rate applied: a rise in the cost of financing, a 5% overrun on the initial investment or a one-year delay in start-up is enough to push NPV negative.

The discounted payback of nearly five years confirms that reading: profitability rests on the year 4 and year 5 flows, that is, on the least certain assumptions. Such an application is not one to reject — it is one to strengthen, either on the initial investment or on the first two years' flows.

Do your four indicators hold together?

We build the financial model on your real data, test the sensitivity of the assumptions, and align the results with the technical part of the study.

Have my profitability calculated →

6. The six most frequent calculation errors

Observations from our practice preparing and reworking studies, not regulatory provisions.

  1. Calculating on accounting profit instead of cash flows. Depreciation charges do not leave the bank account; changes in working capital do. Confusing the two distorts all four indicators at once.
  2. Failing to justify the discount rate. An unexplained rate makes the NPV unverifiable. It must be linked to the actual cost of the resources set out in the financing plan.
  3. Omitting working capital from the initial investment. This is the costliest omission: it understates the outlay and mechanically flatters the payback period.
  4. Ignoring residual value at the end of the horizon. Over five years, equipment retains value. Omitting it penalises the project; overstating it makes it suspect.
  5. Presenting a break-even point incompatible with production capacity. If break-even assumes a utilisation rate higher than the one stated in the technical study, the inconsistency is visible without any calculation.
  6. Not testing sensitivity. A single set of assumptions says nothing about the project's robustness. Varying the selling price, input costs and start-up date immediately reveals where the structure breaks.

This article presents a calculation method and an example using illustrative figures; it constitutes neither investment advice, nor a recommendation to undertake a project, nor a guarantee of results. Any decision must rest on the company's real data and on the financing terms actually obtained.

FAQ — Frequently asked questions

What is the difference between NPV and IRR? +
NPV measures the value created by the project, expressed in dinars, once future flows are discounted at a chosen rate. IRR measures the project's own return, expressed as a percentage: it is the rate that would make NPV zero. NPV depends on the rate chosen, IRR does not — but it must be compared with that rate to be interpreted.
How should the discount rate be chosen? +
The rate represents the minimum return required given the cost of the resources raised and the project's risk. It is generally built from the average cost of financing, own contribution and loan combined, plus a risk premium linked to the activity. None of the texts examined sets a regulatory rate: it must therefore be stated and justified within the study.
Why is discounted payback longer than simple payback? +
Because it accounts for the cost of time. Each future flow is reduced before being accumulated, which mechanically pushes back the point at which the cumulative total reaches the amount invested. Discounted payback is the only version consistent with NPV and IRR.
Is a project with a positive NPV always acceptable? +
A positive NPV means the project creates value at the chosen rate. It says nothing about the safety margin: if the IRR is very close to the cost of financing, a modest change in assumptions is enough to tip NPV negative. That is why the four indicators are read together, not in isolation.
Are these indicators mandatory in an Algerian investment application? +
Part VI of the template in Annex V to Executive Decree no. 26-154 of 14 April 2026 requires a profitability analysis covering IRR, NPV, the break-even point and the margin rate, in addition to a projected income statement, cash flow statement and balance sheet over three to five years.
Over how many years should flows be projected? +
The Annex V template uses a horizon of three to five years for the projected statements. Beyond that, the reliability of assumptions falls sharply; below it, a project whose profitability arrives late is not properly represented.

🔎 Sources and references

📚 Related articles on ProfitPilot

BENSAID Farouk ProfitPilot

BENSAID Farouk

Financial & Economic Research Consultant — ProfitPilot NextGen Consulting

Certified sole trader and expert in financial studies, risk analysis and market research for SMEs, startups and investors in Algeria. View full profile →